> here is the curve showing how we progress towards moving our sites to
> LCG-2_4_0.
>
> Day 0 was the release date (06/04/2005).
> Based on a linear model, we will have on Wednesday the 11th May at
> 18:00 90% of the sites moved to the new version.
> This is a bit too slow to meet the target date 27/04/2005 (15
> work days
> after the release).
>
> markus "I hope it is more