Markus, for reference can you tell us how many sites were successfully
at 230 or 231 before 6/4?

John 

> -----Original Message-----
> From: Markus Schulz [mailto:[log in to unmask]] 
> Sent: 18 April 2005 08:17
> To: LHC Computer Grid - Rollout
> Cc: project-eu-egee-cic-managers; project-egee-roc-managers 
> alternates))
> Subject: LCG2 is moving towards LCG-2_4_0
> 
> 
> Dear Resource Center Staff, Core Infrastructure and Regional 
> Operation 
> Centers,
> here is the curve showing how we progress towards moving our sites to 
> LCG-2_4_0.
> 
> Day 0 was the release date (06/04/2005).
> Based on a linear model, we will have on Wednesday the 11th May at 
> 18:00 90% of the sites moved to the new version.
> This is a bit too slow to meet the target date 27/04/2005 (15 
> work days 
> after the release).
> 
>                                  markus "I hope it is more 
> exponential" 
> schulz
> 
> 
> 
> 
>