Hi Chris,
Thanks for the explanation. Now I am not confused :=)
As before, if there are particular components without suitable upgrade paths, we will need to consider adjusting the update timetable. The important point is to respond to any tickets explaining why it is not possible to upgrade.
Regards
Dave
------------------------------------------------
Dr David Kelsey
Particle Physics Department
Rutherford Appleton Laboratory
Chilton, DIDCOT, OX11 0QX, UK
e-mail: [log in to unmask]
Tel: [+44](0)1235 445746 (direct)
Fax: [+44](0)1235 446733
------------------------------------------------
> -----Original Message-----
> From: Christopher J. Walker [mailto:[log in to unmask]]
> Sent: 05 March 2013 09:55
> To: Testbed Support for GridPP member institutes
> Cc: Kelsey, David (STFC,RAL,PPD)
> Subject: Re: Tickets for the 5th of March
>
> On 05/03/13 07:34, David Kelsey wrote:
> > Hi Chris,
> >
> > I am confused. The current middleware upgrade campaign is to move away
> > from EMI-1 (which is reaching end of security support) to EMI-2.
>
> http://storm.forge.cnaf.infn.it/home:
>
> 29/11/2012 a new issue has been found on StoRM last release 1.10.0, if you
> are willing to update your StoRM installation consider NOT to update StoRM
> FrontEnd component or to wait to our next coming bugfix release StoRM
> 1.10.1
>
> Which has not yet been released in EMI-2.
>
> >
> > The release date of EMI-3 is nothing to do with this.
>
> If I'm not allowed to run EMI-1, and recommended not to run the release in
> EMI-2, I was assuming I'd go straight to EMI-3. Clearly, EMI-3 needs to have
> been released for me to do that.
>
> Chris
>
>
> >
> > Regards
> > Dave
> >
> >
> >
> > ------------------------------------------------
> > Dr David Kelsey
> > Particle Physics Department
> > Rutherford Appleton Laboratory
> > Chilton, DIDCOT, OX11 0QX, UK
> >
> > e-mail: [log in to unmask]
> > Tel: [+44](0)1235 445746 (direct)
> > Fax: [+44](0)1235 446733
> > ------------------------------------------------
> >
> >
> >> -----Original Message-----
> >> From: Testbed Support for GridPP member institutes [mailto:TB-
> >> [log in to unmask]] On Behalf Of Christopher J. Walker
> >> Sent: 04 March 2013 22:41
> >> To: [log in to unmask]
> >> Subject: Re: Tickets for the 5th of March
> >>
> >> On 04/03/13 20:18, [log in to unmask] wrote:
> >>> Christopher J. Walker [mailto:[log in to unmask]] said:
> >>>> Any possibility of extending security support by however late EMI-2
> >> is?
> >>>
> >>> Do you mean EMI 3?
> >>
> >> Yes, sorry, I did.
> >>
> >>> If so I think it will be out in the next few days
> >>> - given the impending end of the project there isn't much scope for
> >> delay.
> >>
> >> The current lateness has already reduced the time I have to upgrade
> >> by 25%!!!
> >>
> >> One month was already tight - assuming, that is, I wish to run
> >> software in security support, and ignoring other things that need to
> >> be done in that time.
> >>
> >> In my case, StoRM is the software I'm concerned about, but no doubt
> >> there's other software in a similar position (the WMS perhaps).
> >>
> >> Chris
--
Scanned by iCritical.
|