Dear All,

As mentioned at Tuesdays Ops meeting I've just sent out the Site Hardware Survey's (see below email and attached spreadsheet). Emails were sent to the registered site contact taken from the GOCDB so if you didn't receive it from that route you may want to check the GOCDB entry.

If you could return to me by the 24/July/2019 so I can process them all, it would be greatly appreciated. If you have any questions let me know!

Thanks,

Gareth



=====

Dear <Your Site> Site Admins,

As part of the preparation for generating the GridPP 2019/20 pledges to the WLCG we would like to carry out a survey of the current available hardware (as we've done in the previous years) to get an idea of the present state of GridPP resources.

If you could complete this survey based on your current hardware inventory for CPU, Disk and network capacity and show how you plan to retire that capacity based your sites policies by the 24th July 2019 so that I can collate and report to the PMB it would be appreciated.

I've included a worked example showing Glasgow's current status as a sample response, additionally if your site has received IRIS funding if you could separate out that equipment in your response.

If you have any questions, please contact me.

Thanks,

Gareth
Acting GridPP Project Manager


########################################################################