The draft WLCG a & R report is below

ALICE

All OK

 

ATLAS

QMUL 87%, 87%

 

CMS

All OK

 

LHCb

QMUL 75%,75%

 

As usual please let us know the issues encountered if your site is mentioned above and/or you intend to request a re-computation.

 

Many thanks,

Pete

 

 

--

----------------------------------------------------------------------

Peter Gronbech  GridPP Project Manager          Tel No. : 01865 273389

 

Department of Particle Physics,                         

University of Oxford,                 

Keble Road, Oxford  OX1 3RH, UK  E-mail : [log in to unmask]

----------------------------------------------------------------------

 

From: WLCG Office <[log in to unmask]>
Sent: 04 May 2018 16:13
To: project-wlcg-cb (Members of the WLCG CB) <[log in to unmask]>
Cc: project-lcg-gdb (LCG - Grid Deployment Board) <[log in to unmask]>; monit-support (Email address for monit support) <[log in to unmask]>
Subject: WLCG T2 availability & reliability - April 2018

 

Dear all,

 

The draft availability and reliability reports for April are now available at:

 

http://wlcg-sam.cern.ch/reports/2018/201804/wlcg/

 

Please check your data and send any comments to [log in to unmask] by 14 May.

 

Any requests for recomputation must be submitted via GGUS within the next 10 calendar days; full details here: https://twiki.cern.ch/twiki/bin/view/ArdaGrid/RequestProfileCorrections  

 

Kind regards,

Cath

 

 


-----------------------------------------------
WLCG Office
IT Dept - CERN
CH-1211 Genève, Switzerland
www.cern.ch/wlcg