The draft WLCG a & R report is below
ALICE
All OK

ATLAS
QMUL 87%, 87%

CMS
All OK

LHCb
QMUL 75%,75%

As usual please let us know the issues encountered if your site is mentioned above and/or you intend to request a re-computation.

Many thanks,
Pete


--
----------------------------------------------------------------------
Peter Gronbech  GridPP Project Manager          Tel No. : 01865 273389

Department of Particle Physics,
University of Oxford,
Keble Road, Oxford  OX1 3RH, UK  E-mail : [log in to unmask]<mailto:[log in to unmask]>
----------------------------------------------------------------------

From: WLCG Office <[log in to unmask]>
Sent: 04 May 2018 16:13
To: project-wlcg-cb (Members of the WLCG CB) <[log in to unmask]>
Cc: project-lcg-gdb (LCG - Grid Deployment Board) <[log in to unmask]>; monit-support (Email address for monit support) <[log in to unmask]>
Subject: WLCG T2 availability & reliability - April 2018

Dear all,

The draft availability and reliability reports for April are now available at:

http://wlcg-sam.cern.ch/reports/2018/201804/wlcg/

Please check your data and send any comments to [log in to unmask]<mailto:[log in to unmask]> by 14 May.

Any requests for recomputation must be submitted via GGUS within the next 10 calendar days; full details here: https://twiki.cern.ch/twiki/bin/view/ArdaGrid/RequestProfileCorrections

Kind regards,