Dear All,

As mentioned at the ops meeting, the November stats have been circulated. Here is the summary:

ALICE (http://wlcg-sam.cern.ch/reports/2015/201511/wlcg/WLCG_All_Sites_ALICE_Nov2015.pdf):

All okay.

ATLAS (http://wlcg-sam.cern.ch/reports/2015/201511/wlcg/WLCG_All_Sites_ATLAS_Nov2015.pdf):

Sheffield: 79%:79%
RALPP: 86%: 86%

CMS (http://wlcg-sam.cern.ch/reports/2015/201511/wlcg/WLCG_All_Sites_CMS_Nov2015.pdf):

All okay.

LHCb (http://wlcg-sam.cern.ch/reports/2015/201511/wlcg/WLCG_All_Sites_LHCB_Nov2015.pdf):

RALPP: 88%:88%


So very good overall.

Regards,
Jeremy





Begin forwarded message:

From: WLCG Office <[log in to unmask]<mailto:[log in to unmask]>>
Subject: T2 reliability & availability - November 2015
Date: 1 December 2015 10:34:57 GMT
To: "project-wlcg-cb (Members of the WLCG CB)" <[log in to unmask]<mailto:[log in to unmask]>>
Cc: "project-lcg-gdb (LCG - Grid Deployment Board)" <[log in to unmask]<mailto:[log in to unmask]>>, "[log in to unmask]<mailto:[log in to unmask]>" <[log in to unmask]<mailto:[log in to unmask]>>, "[log in to unmask]<mailto:[log in to unmask]>" <[log in to unmask]<mailto:[log in to unmask]>>, "sam-support (SAM support)" <[log in to unmask]<mailto:[log in to unmask]>>

Dear all,

The draft T2 reliability & availability reports for November 2015 are now available at:


http://wlcg-sam.cern.ch/reports/2015/201511/wlcg/


Please check your data and send any comments to [log in to unmask]<mailto:[log in to unmask]> by 11 December.


Any requests for recomputation must be submitted via GGUS within the next 10 calendar days; full details here<http://tomtools.cern.ch/confluence/display/SAMDOC/Availability+Re-computation+Policy>.


Kind regards,

Cath



-----------------------------------------------