Print

Print


Hi John,

Each test we (Liverpool) do relates to  one atomic release of a product. 
If a
patch is applied,  it needs another release of the product to get the 
patch out,
and a new test test (we use no other test/reject/patch/testagain cycle).
Tests that Liverpool completed in the Aug-Oct timeslot were:

*EMI.cream.sl6.x86_64-1.16.1 
<https://rt.egi.eu/rt/Ticket/Display.html?id=5791>
*https://rt.egi.eu/rt/Ticket/Display.html?id=5791

*EMI.bdii-site.sl6.x86_64-1.2.1 
<https://rt.egi.eu/rt/Ticket/Display.html?id=5864>
*https://rt.egi.eu/rt/Ticket/Display.html?id=5864

Cheers

Steve




On 11/07/2013 07:58 PM, John Gordon wrote:
> I have a couple of metrics to report to EGI on Staged Rollout in the UK.
>
> a)      Total number of software components tested/rejected in staged rollout in this NGI
>
> b)      Number of staged rollout tests undertaken. (A single patch can be tested by multiple EA sites at a time. This metric counts the number of actual tests performed by the EA sites)
>
> This useful table gives me some information
>
> https://www.gridpp.ac.uk/wiki/Staged_rollout_emi3
>
>  From it I can see that in the previous quarter Aug-Oct the UK tested 8 components and if I count multiple sites then we did 12 tests.
>
> However this may be hiding repeated releases (test/reject/patch/testagain) within a month.
>
> Can I ask for help please? If any of the sites listed as testing in Aug, Sept, or Oct did more than one cycle can they please mail me with the number.
>
> Or if there is somewhere I can find this out without reading every staged rollout report in the document database, I would be glad to hear about it.
>
> Many thanks,
>
> John
>


-- 
Steve Jones                             [log in to unmask]
System Administrator                    office: 220
High Energy Physics Division            tel (int): 42334
Oliver Lodge Laboratory                 tel (ext): +44 (0)151 794 2334
University of Liverpool                 http://www.liv.ac.uk/physics/hep/