Dear all,
Please find below the draft T2 Reliability & Availability report for August 2012:
Requests for re-computations are to be entered via GGUS within 10 calendar days of this e-mail being sent. Full details are here: https://tomtools.cern.ch/confluence/display/SAMDOC/Availability+Re-computation+Policy
The final T2 reports are stored in the WLCG document repository under http://cern.ch/wlcg-docs/ReliabilityAvailability/Tier-2 and reported to the Overview Board.
Kind regards,Cath
-----------------------------------------------