Hi,

What is the plan/requirment on sites to provide alternative resources?  Glasgow's WMS do not support all VO's is there a requirement to allow more VO's, if so which ones?  Glasgow also has a top level BDII.  Other sites can reconfigure to use it but as RAL has a load balanced system and we do not I would suggest that we spread the load across other tier2 sites in order to avoid crashing ours.

Regards,

Dug

2009/5/26 Derek Ross <[log in to unmask]>
Hi,

Details of the Tier 1's extended downtime for the machine room move in June/July, the main points that will potentially affect other sites are the draining of the WMS from the 17-26th, and the downtime for Myproxy and top-level BDIIs on the 25th, and the LFC & FTS downtimes on the 25-26th.

Sites may wish to consider reconfiguring their UIs and WNs to avoid problems.

Derek





Begin forwarded message:

From: "Smith, GR (Gareth)" <[log in to unmask]>
Date: 19 May 2009 12:17:43 BST
To: <[log in to unmask]>, <[log in to unmask]>
Subject: RAL Tier1. Details of outage during move to new computer building.

Hi,

The RAL Tier1 will be moving to a new computer building at the end of
June and beginning of July. The move will entail a significant outage of
the services: Castor will be unavailable for twelve days and the batch
system for around two weeks.

For the details of the outages please see the entry in the Tier1 blog
at:
       
http://www.gridpp.rl.ac.uk/blog/2009/05/14/schedulemovenewbuilding/

To ensure as many people as possible are aware of this I have sent this
mail to both the gridpp-ub and gridpp-users lists. My apologies if you
receive it twice.

Gareth Smith
RAL Tier1 Production Manager.

--