Do you know the date for when CNAF mad e the change?
Brian
-----Original Message-----
From: Testbed Support for GridPP member institutes [mailto:[log in to unmask]] On Behalf Of Christopher J. Walker
Sent: 22 April 2013 17:49
To: [log in to unmask]
Subject: Re: Tickets for the 23rd of April
On 22/04/13 16:40, Christopher J. Walker wrote:
> On 22/04/13 15:48, Matt Doidge wrote:
>
>> RHUL
>> https://ggus.eu/ws/ticket_info.php?ticket=89751 (17/12/12) Govind had
>> been informed that the path MTU discovery to RHUL should work, but
>> Chris has reported that he still sees the problem. It might be useful
>> to find out where the external box that the RHUL network admins used
>> for their test resides. In progress (17/4)
>
> It also appears that Janet think the request was to enable jumbo
> frames ( MTU=9000 )to RHUL. That would solve me issue for me, but so
> would getting path MTU discovery to work.
>
I should add that CNAF have now turned Jumbo frames on for their GridFTP servers.
Chris
--
Scanned by iCritical.
|