Ewan, you have commented on my reply without initial statement
I was replying to Matt statement :
"SHEFFIELD: Elena has closed their ticket after upgrading everything."
to say that I have a work to be done in Sheffield and not giving a recipe how to close a ticket.
Sorry if it was not clear.
Elena
On 19 Nov 2012, at 18:01, Ewan MacMahon wrote:
>> -----Original Message-----
>> From: Testbed Support for GridPP member institutes [mailto:TB-
>> [log in to unmask]] On Behalf Of Elena Korolkova
>>
>> I've EMI CE and DPM Head node. That's enough to close the ticket as I
>> don't see warnings at security board.
>>
>
> At the moment the critical bit of this is that you've done the CEs;
> even if you had a gLite 3.2 SE head node you could close the ticket,
> because the gLite 3.2 DPM doesn't count as critical yet.
>
> However, it will count as critical from the beginning of December,
> and at that point sites should have upgraded their entire DPM, pool
> nodes included. The monitoring can't check them as easily as it can
> head nodes, but that doesn't mean that running them will be OK - the
> objective here is to get rid of the old middleware, not to clean up
> the dashboard.
>
> Ewan
__________________________________________________
Dr Elena Korolkova
Email: [log in to unmask]
Tel.: +44 (0)114 2223553
Fax: +44 (0)114 2223555
Department of Physics and Astronomy
University of Sheffield
Sheffield, S3 7RH, United Kingdom
|