Dear all (but mainly Andy, I guess):
There is still GPL-ed code in dawn-fable. Is there any chance that this
could be sorted out by 15 June? I have attached the last e-mail
correspondence about this from the old DAWB mailing list on 7 Feb.
Regards,
Peter.
On Thu, 2012-04-26 at 15:32 +0000, Alun Ashton wrote:
> Don’t shoot the messenger.
>
>
>
> So after consideration and disscussion please find enclosed the
> suggested revised release schedule for DAWN 1.0, let me know what you
> think of if you want to discuss your individual timetables and how
> they fit in. (Thanks to Andy, Matt and Mark for their help on drafting
> this).
>
>
>
> 18th May: 1st Release candidate
>
> 8th June Release Candidate 2 –final?
>
> 15th of June: Release date.
>
>
>
> If I am honest I think that for release candidate 1 we should have all
> the functionality and features in but between release candidate 1 and
> the release date we should work on bug fixes and ‘branding’,
> installation etc. I don’t think there is time to get that all done by
> RC1.
>
>
>
> There are 5 components each of which should have its own sub release
> schedule and can start its own thread on this mailing list, but in
> summary:
>
> 1) Plotting (this is referring to the ‘new’ plotting led by MattG,
> any other changes to e.g. fable plotting or SDA plotting should adhere
> to the same Release candidate and main release dates).
>
> a. 4th May ‘soft’ freeze on new functionality, all contributions
> should be in by this date (Sandor/Gabor/Jonathon we should try and get
> any contributions you wish to make in by this date), Matt has a list
> of functionality if anybody needs it.
>
> b. 11th May ‘hard’ freeze on any new functionality.
>
> 2) Workflow (led by Olof)
>
> a. I will assume Olof will come up with a plan etc that will
> correspond to the release dates.
>
> 3) Python (led by Mark, he will start a separate thread with
> details etc)
>
> a. 11th of May, ‘soft’ freeze on new functionality
>
> b. 18th of May, hard freeze.
>
> 4) ICAT (led by Ghita, I have this as separate but we can decide
> later if needs to be)
>
> a. 27th of April freeze on functionality and release of plugin.
> Basically this is done for integration with ICAT 3*
>
> 5) Product (including views and perspectives)
>
> This is where there is a bit of ‘flexibility’/unknown! This section
> should include new and old views, existing perspective, new
> perspectives, documentation including cheat sheets, logo!, welcome
> screen, installation, packaging etc.
>
> a. 11th May: freeze for converting existing views and
> incorporating new views.
>
> b. 17th May: freeze on testing and documentation and preparation
> of build
>
> c. 18th May: Release candidate 1
>
> d. 8th of June: Release candidate 2 with all build, perspectives,
> welcome screen, logo etc, its should be as close to the actual release
> as possible.
>
>
>
> No doubt I will have missed some things out….
>
>
>
> Alun
> ___________________________________________________________
> Alun Ashton, [log in to unmask] Tel: +44 1235 778404
> Scientific Software Team Leader, http://www.diamond.ac.uk/
> Diamond Light Source, Chilton, Didcot, Oxon, OX11 0DE, U.K.
>
>
--
Peter Keller Tel.: +44 (0)1223 353033
Global Phasing Ltd., Fax.: +44 (0)1223 366889
Sheraton House,
Castle Park,
Cambridge CB3 0AX
United Kingdom
|