Dear Justin,
Both Wim and Tim just left for holidays, so I shall have to give it a try.
I do not know the DataShifter, but here is a possible fix:
When you transfer the PeakList you presumably tell it which experiment
(and DataSource) the PeakList should be connected to. The way things work,
the new resonances ought to appear in the ShiftList that is connected to
the target Experiment. Could you check which that is? And if you prefer
ShiftList 1, could you not select that as your ShiftList, creating a new
one if there is no ShiftList none, then select it.
Hopefully this helps, otherwise I might have to start looking at teh
DataShifter.
Yours,
Rasmus
---------------------------------------------------------------------------
Dr. Rasmus H. Fogh Email: [log in to unmask]
Dept. of Biochemistry, University of Cambridge,
80 Tennis Court Road, Cambridge CB2 1GA, UK. FAX (01223)766002
On Thu, 23 Aug 2007, Justin Douglas wrote:
> Hi Wim,
>
> This post is related to one I made a couple of weeks ago that might have
> slipped through the cracks....
>
> At any rate, I would like to use datashifter to transfer a peaklist (with
> assignments) from one project to another. As far as everything in
> datashifter goes it seems OK, but when I open the project all the resonances
> are in shiftlist:none. I don't recall datashifter asking me where I wanted
> the resonances put and I had used datashifter previously to transfer
> peaklists and there was no problem.
>
> So my question is two-fold
>
> #1) Is there an analysis-specific way to transfer resonances from
> shiftlist:none to shiftlist:1?
>
> #2) Is there a datashifter-specific way to transfer peaklists and get all
> the resonances in the desired shiftlist?
>
> Thanks,
>
> Justin
>
|