Hi,
in the release note of LCG-2_5_0 I have stated that 2_6 will come
early July.
This statement was deliberately vague because at that time the state
of the some of the components meant to go into the release was less
than clear.
Our aim is to release at the 15th to the 3 ROCs that volunteered for
deployment testing and then with their feedback release at the
20th. The ROCs will then plan for their region the schedule taking
into account the regional users and sites.
markus
On Jul 8, 2005, at 1:27 PM, Alessandra Forti // EOJ wrote:
> Hi,
>
> can anyone from the deployment team at CERN update us on the
> situation of LCG-2_6_0?
>
> I need to schedule manpower and agree with some of the experiments
> when to do the upgrade. The release was due this week but there is
> no sign of it and I haven't seen any email that explains why it has
> been delayed and when it is foreseen for and what we should expect
> from it. It would be very helpful to know. An EGEE broadcast would
> be apreciated.
>
> thanks
>
> cheers
> alessandra
>
> --
> ********************************************
> * Dr Alessandra Forti *
> * Technical Coordinator - NorthGrid Tier2 *
> * http://www.hep.man.ac.uk/u/aforti *
> ********************************************
>
|