Joe, you need to change the status in GOCDB. Go to
http://goc.grid-support.ac.uk/gridsite/gocdb/ and 'enter the GOCDB'. If
it recognises you as manager for FNAL then it will display FNAL
information - click 'certify and uncertified site'. The same page lets
you set production too.
Good luck,
John
> -----Original Message-----
> From: LHC Computer Grid - Rollout
> [mailto:[log in to unmask]] On Behalf Of Joseph
> L. Kaiser
> Sent: 17 May 2005 17:35
> To: [log in to unmask]
> Subject: [LCG-ROLLOUT] Uncertified, Pre-Production
>
> Hi,
>
> In the GOC we are listed as:
>
> status: Uncertified, type: Pre-Production
>
> How do we become Certified Production?
>
> Thanks,
>
> Joe
>
|