We have done a one-way migration ( that is: to new hardware )from a dual
server (seperate database & application server) running Windows 2000 / Ms
Sql server 2000 to a single server running Windows 2000 / Ms Sql server
2000.
We migrated 700 courses, 20.000 users. The actual migration proces lasted
for about 3 hours. We did not encounter any problems. ( Migration time
will depend on the speed of the network connection. Used was a 1Gb/s
connection between the 3 servers. )
Configurating the new Blackboard server took longer ( look & feel, which
options will be available to which sort of user etc. ) but most of it can
be done in advance. Time spent on configuration after migration: about 2
hours.
Instructors are happy with the new version, especially being able to
change the text in the course buttons and being able to copy items in and
between courses.